Concrete Cooling by Flake Ice and Cold Air
Click on the pictures to enlarge
Concrete Cooling by Flake Ice and Ice Water
Complete mobile concrete cooling system with flake ice plant, 60 tons ice storage, ice water plant and cold water tank, 2003-2005
What does a concrete cooling system look like?
In general each concrete cooling system for dam construction and for mass concrete consists of the following components:
• Water Chilling Plant for the total amount of mixing water
• Cold Water Tank with Pumping Station
• Flake Ice Plant
• Flake Ice Storage with fully-automatic Ice Rake and Discharge System
• Flake Ice Delivery
• Flake Ice Weighing
• Aggregate Cooling System
•
Post-Cooling of the concrete
Of course, there are always different options available for each component.
Concrete Mixing Temperature as function of water temperature and addition of ice respectively
Temperature-Controlled Concrete
Supplying temperature-controlled concrete for the construction of large dams is a must all over the world. The development of the strength inconcrete is accompanied by evolution of heat as the cement cures and hardens (heat of hydration). In small structures this phenomenon is not of importance, but very significant in mass concrete especially for dam projects. The heat of hydration raises the temperature during the curing process by up to 25° causing an increase of volume. After the curing the concrete cools down again reducing its volume and thus naturally causing cracks eventually. Therefore the initial pouring temperature should be lowered so much that the maximum temperature during the curing process does not exceed a certain temperature determined by the consultants.
Even though the required pouring temperatures of the concrete vary from site to site and from country to country (from +7°C to max. 15°C) there is always a requirement for a sophisticated refrigeration system.
As the initial and the running costs for such a refrigeration system are quite high (they even can be higher than the ones of the concrete batching plant itself) it is essential for the contractor to have an optimised system installed.